Road Construction | MIL001
Taan Forest Limited Partnership (Taan) is requesting road building contractors propose an all found rate for road construction by linear meter of road ($/LM) to construct 3134 metres of new road including MIL001-1, MIL001-1A, MIL001-1B, MIL003-1:
Sub Grade construction
Utilization of non-merchantable timber for puncheon
Culvert Installation
Bridge Installation
Local ballast/ rock gravel development
Ballast hauling and spreading
Decking merchantable ROW timber at roadside
Prime Contractor responsibilities
Taan’s Corporate Management System including crew training (CMS Level 1 and Supervisors training CMS Level 2)
Familiarization of the BC Ministry of Forest Engineering manual, specifically to sub grade construction, culvert installation, simple crossing installations
Culverts will be supplied by Taan Forest, contractor will be responsible for delivery to site from Juskatla.
Logs for Wooden Box Culvert (WBC) will come from on site, construction of the WBC is the responsibility of the contractor.
Taan will be responsible for the ROW falling and processing and any rock development outside the block boundaries. Should an external pit greater than 3.2 km away from block be required a haul rate will be negotiated with the successful contractor to haul rock from the designated quarry.
All wood will remain the property of Taan Forest and will be marketed at their discretion
Proposals must include:
Cover letter with summary
Ability to complete work (list of Equipment and previous experience)
Commitment to hire local (people who live on Haida Gwaii) including number of people who will be working on this block.
$/Linear Metre for road construction (Row falling, Subgrade, culvert installs, ballasting)
BC Forestry Safety Council Safe Company number
Worksafe BC number
References
In no specific order proposals will be rated on:
Ownership of contract (Haida Owned and Local Haida Gwaii ownership take precedence)
Past experience / performance with Taan Forest
Ability to hire local and number of local people employed with this work. Preference to Haida workers
Ability to complete the work with available resources.
Linear Metre construction rate – New Road
Road Specifics:
Total length of proposed new roads = 3134m
MIL001-1 = Start 0+000 Stop 1+946 (1946m)
MIL001-1A = Start 0+000 Stop 0+746 (746m)
MIL001-1B = Start 0+000 Stop 0+282 (282m)
MIL003-1 = Start 0+000 Stop 0+160 (160m)
All roads must be constructed to Taan standards as per Road Instructions
Term – Anticipated Start Date February 15, 2024
end date April 30, 2024
Deadline for Submission: February 5, 2024 @ 3:00pm. Parties will be contacted after February 7, 2024 based upon their submissions and advised of next steps
Submit to:
By e-mail: info@taanforest.com Subject MIL001 Road Construction Opportunity, Attention Operations Supervisor
In Person: - Taan Office Unit 3 848 Highway 16 – Enclosed in envelope, Attention Operations Supervisor
Questions, Additional Information and viewings:
Jud Jones (250) 626-7527 or Jerome Benoit (778) 260-0046
Private Property must be accessed to view this road, please schedule a viewing.
Attch:
Road Instructions
Overview Map
General Contract particulars